Also, Zortek Systems and Thyssen worked in the installation of two walkways to unite the bridges with the Terminal Building . During the whole project, Zortek Systems personnel assisted airport operators in operations, installation and design. All of this added value effort was seen in the perfect installation and final commissioning of the bridges.
Mr. Rodolfo Oliva assumed as Project Leader. The project was also supported by Mr. Juan Manuel Ortiz ( On-Site Project Manager ) – in charge of the installation, and Mr. Armando Navarro ( Business Manager ) – assuming the direction and logistic of the operations of the project.
Zortek Systems also took part in other projects regarding the expansion, such as the installation of baggage conveyors for the International Arrivals area, in which Zortek helped Siemens (Mexico division) in the commission of the system. In that way, ten counters for customs inspection were built by Zortek Systems personnel in Cali and are now in process of arrival to Tegucigalpa to operate at the airport. All these achievements show once again the vast experience and professionalism of the Zortek Systems personnel in wide-range projects.
|