The LPA Group - Aviation Projects
 


CONTRACT WITH: The Bi-Courtney Consortium
TO: Murtala Mohammed International Airport
COUNTRY / CITY: Nigeria/Lagos
CONTRACT VALUE : US 2.500.000
EXECUTION TIME : Since 10/2006 to 10/2011


CONTRACT DESCRIPTION :

Operation and general services of advising and consultancy in the Management, Operation, Maintenance, Supervision and Security areas.

CONTRACT WITH: AERODOM SIGLO XXI
TO: Samana Airport
COUNTRY / CITY:Dominic Republic.
CONTRACT VALUE: US 183.000
EXECUTION TIME : Since 10/2006 to 12/2006

CONTRACT DESCRIPTION :

The operation of the PAS technology permits the airport improves the system of information, locating and evacuation system.  The system consists of a "code of locating" to any loudspeaker or area of the airport.  This installation includes IP phones, automatic amplified and centralized Loudspeakers, modulation and discrimination for the devices of the area, and besides routing devices. 

On the other hand, the EVIDS technology offers to the airport a system of complete fligth information, luggage, shipment gates, and about the tickets.  The graphic interface of user will reduce the time of training and human errors.  The systems can be configured easily and to show quickly any class of information to the passengers as for any terminal, optimizing the performance of the administration of the airport.

CONTRACT WITH: International Civil Aviation Organization (ICAO).
TO: Tocumen International Panama Airport
COUNTRY / CITY: Panama / City of Panama
CONTRACT VALUE : US 8.400.000
EXECUTION TIME : Since 02-2006 to 01-2008 


CONTRACT DESCRIPTION :

The contract includes the engineering and the installation of the systems, the delivery and installation of the equipments, software, start up, commissioning and a special program including guarantee, spare parts, technical support, remote maintenance and site support 24/7 365 days to the year, during a period of 5 years. 
With this type of contract, the administration of the Tocumen Airport assures the continuity of the operation and the maintenance of the systems acquired by a reasonable period and avoids disbursements done not predict during the period arranged.  This scheme of maintenance and support post sale, where the replacements are included and the updating of the systems, is already a practice in airport installations performed by ZORTEK SYSTEMS. 

The main components of the Airport System of Management and Information include a network of wiring with primary modules and modules of interface, a system of common use of equipment and airlines counters(CUTE), a visual system of information to the public and of information of luggages (FIDS/BIDS/VIDS), a central Database server  with operational informations (AODB), a Gate Management System and departures (GMS), Sound of the passenger Terminal (PAS), access control system, circuit closed of television (CCTV), sales points system (POS), system of master clock, system of automatic billing, system SCADA and system of communications VOIP.


CONTRACT WITH: IASA
TO:Toncontin International Airport
COUNTRY / CITY: Honduras/ Tegucigalpa        
CONTRACT VALUE : US 730.000

EXECUTION TIME : Since 10/2005 to 01/2006

CONTRACT DESCRIPTION:

On January 24, 2006, the Airport International Toncontín inaugurated the Enlargement of the passenger Terminal, destined on the way out and arrival of international passengers.  Zortek Systems, in I associate with the multinational business ThyssenKrupp, contributed to the enlargement delivering two Passenger Boarding Bridges type Apron Drive in a time record from two months to the New Dealer Airports of Honduras.  Also Zortek participated in the installation of the fixed gateways that join the bridges with the terminal.


During all the development of the project, Zortek provided technical support in design, operations and installation, what is translated like aggregate value on the ending of the project and start up of the bridges

CONTRACT WITH: AERODOM SIGLO XXI
TO: Isabela Airport
COUNTRY / CITY: Dominic Republic
CONTRACT VALUE : US 195.000
EXECUTION TIME : Since 09/2005 to 02/2006


CONTRACT DESCRIPTION:

Supply, installation and Start up of Flight Information Display System

 

CONTRACT WITH:"El Cibao" International Airport
TO: 'el Cibao' International Airport
COUNTRY / CITY: Dominic Republic/ Santiago de los Caballeros
CONTRACT VALUE : US 885.000
EXECUTION TIME : Since 05/2005 To 03/2006


The International Airport 'The Cibao', decided to expand its installations and equipment to include greater capacity and thus to be able to increase the level and quality of the service to its users, such as the passengers and airlines.   Zortek installed n this airport 3 Passenger Boarding Bridges, a system of common use of counters for the airlines, called 'Common User System' (CUTE) and a System of Local Checkup "Local DCS" LDCS (SEATS).

CONTRACT WITH: IASA
TO: 4  International Airports from Honduras
COUNTRY / CITY: Honduras
CONTRACT VALUE : US 263.000
EXECUTION TIME : Since 01/2005 to 06/2005

CONTRACT DESCRIPTION :

Supply and installation of Signs group to the Platform, to four (4) International Airports of Honduras.

CONTRACT WITH: The Bi-Courtney Consortium
TO: Murtala Mohammed Airport
COUNTRY / CITY: Nigeria/Lagos
CONTRACT VALUE : US 5.300.000
EXECUTION TIME :
Since 09/2004 to 02/2008


CONTRACT DESCRIPTION :
In the Nigeria International Airport was carried up the follows works:

  • EASÍ -  Entired Automated Sistem of Integration
  • AODB -  Automated Operacional DataBase
  • EVIDS – Electronic Visual Interface Display System
  • CUTE- Common Use Terminal Equipment
  • BRS – Baggage Reconciliation System
  • BHS – Baggage Handling System
  • PBB – Passenger Boarding Bridges
  • IP/PAS  - Telephony and Public Anouncement System
  • PAS – Public Address and Sound System
  • IPA – Intelligent Public Announcement
  • FAS – Fire Alarm System
  • CCTV – Closed Circuit TV
  • ACAM – Access Control and Monitoring
  • PCS – Parking Control System
  • X-RAY – Metal Detection System

CONTRACT WITH: QUIPORT
TO: Mariscal Sucre International Airport
COUNTRY / CITY: Ecuador / Quito
CONTRACT VALUE : US 3.500.000
EXECUTION TIME : Since 05/2003 to 07/2004


CONTRACT DESCRIPTION :

Supply, installation and start up of systems for the airport that includes:  Systems of CUTE, FIDS, CCTV AND IPA